Attribute-Based Activities Solution

In this solution, the activity time or other activity action is based on the value of a particular attribute. (For routings based on activity attributes see conditional routings.) For example: moldings entering an inspect and clean operation are either defective or non-defective. The activity time for defective molds is normally distributed with a mean of 2 minutes and a standard deviation of .5 minutes. Non-defective molds have a mean activity time of .6 minutes with a std. dev. of .2 minutes.


 